| 
    Why is Extra Gas Needed 
    for MIG Weld 
    Starts? 
    We 
    are often asked 
    why certain devices such as restriction orifices mounted at the feeder to 
    control flow do not work or why welders complain about their use.  The 
    following are some answers: | 
  
    | 
    Question: 
    
    Why is some extra gas needed at the weld start? 
    Answer: Some  devices designed to reduce 
gas waste  supply  insufficient extra gas at the weld start to counteract the  air entering the torch 
nozzle, body and  cable when welding is stopped or in the weld start area.  Some of these devices 
control flow at the wire feeder.     Stauffer in a patent published in 
1982 ( Patent Number 4,341,237) discusses this issue.  He clearly 
understood the problem and designed around it using a "surge storage tank"; he states in the patent teaching (see pic below.)
    
    "... air leaks back into the torch and lines when 
welding is stopped.  The air must be quickly purged and replaced with inert 
gas to produce high quality welds.
    
Also, it is 
critical to displace the air at the weld zone of the work piece upon initiating 
the weld. 
    "  
     | 
  
    |  The patented device by Stauffer employed a "surge storage tank" to store extra gas when welding stopped and delivered it back at each start. He define the need in his patent teaching.
 This device improved weld start quality, unfortunately is operated at lower than 25 psi and did not incorporate "automatic flow compensation." | 
  
    | 
    Question: 
    What are the devices that cause lack of sufficient 
    extra gas at the weld start? 
    Answer:  Any device that 
    attempts to control flow at the wire feeder will not have sufficient "stored 
    gas" that can be quickly delivered to the welding torch cable, torch nozzle 
    or weld start area.  This can be a:Flowmeter,
 Orifice that is controlling gas flow,
 Needle valve or
 Regulator/ flowgauge (low or 
            high pressure.)  Note, low pressure regulator devices have added problems. 
              (See Q&A About Automatic Flow 
                Compensation)
 | 
  
    | 
    Question:  We're 
    using a flowmeter at the gas source (cylinder or pipeline.)  Do we have 
    a lack of start gas problem? 
    Answer:  No you probably have 
    much more than enough excess gas but the initial flow surge velocity is so 
    high your pulling moisture laden air into the weld start area and creating 
    similar problems. You can hear the gas surge when you pull the torch 
    nozzle - (CAUTION be sure the wire feeder pressure roll is disconnected 
    when you listen and do not touch an electrically energized part of the torch 
    to your body!!)   
    You Need Our Gas 
    Saver System (GSS), 
    Check It Out. | 
  
    | 
    Question: 
    
    What happens if we don't quickly have sufficient extra gas at the weld 
    start? 
    Answer:  You're essentially 
    starting the weld in moisture laden air until the MIG gun cable, gun nozzle 
    and weld start area get fully displaced by the shielding gas.  About 5% 
    air is sufficient to create Nitrogen porosity
    (See 
    Reference.)  Welders often see this problem and try to counter 
    with higher steady state flow rate settings.  That is only partially successful 
    and the higher steady state flow rate wastes gas! They may also increase the 
    rate so high they create turbulence in the shielding gas stream  This 
    only pulls in moisture laden air and is counterproductive. | 
  
    | 
    Question: Is that 
    why when we have used orifices mounted at the wire  feeder to control 
    shielding gas flow welders complained and sometimes drilled out the orifice? 
    Answer:   
    We have found that to be the 
    case.  Welders may drill out the orifice believing they need higher gas 
    flow (which they may - but just at the start.)  However the smallest 
    drill commonly available in a drill bit set is 1/16 inches.  Sounds 
    like a small hole but on a 50 psi shielding gas pipeline that will provide 
    in excess of 150 CFH flow!  This not only wastes gas but also pulls in 
    moisture laden air creating internal if not visible weld porosity and excess starting spatter similar to the lack of extra gas.. Welders have no doubt experienced what the lack of start gas can cause. They may have started to weld and forgot to open the gas cylinder, a common occurrence. Starting to weld without sufficient extra start gas to purge the gun nozzle and weld start zone is like welding for a few seconds with the gas cylinder shut off! When managing a filler metals and welding process R&D Lab I would occasionally be asked to look at a new flux cored wire of even sold wire. I would put on a ab coat, gloves and helmet and prepare to weld. One of our highly skilled technicians would purposely have the gas cylinder turned off as a "joke" when the "boss came to weld!" It took a few seconds for me to see that excess spatter through the darkened helmet! | 
  
    | 
    Question: 
    
    Are there specific 
    production instances where a switch to some extra gas at the start helped 
    weld performance? 
    Answer:  Yes, the  following 
    two examples
    
    validate the need for some extra gas at the weld 
    start: 
    First Case: 
     A 
bar joist manufacturer was using flow control orifices mounted at the wire 
feeders.  Argon/CO2 shielding 
 gas is supplied in a pipeline 
through about 15 feet of gas delivery hose.  The flow control orifice 
established the flow at 45 CFH.  However the welders wanted higher flow 
rates with some even drilling out the orifice!  The welding engineer wanted to avoid wasting 
shielding gas. With this flow setting arrangement where control is mounted at 
    the feeder next to the gas solenoid  there is insufficient extra gas provided at the weld start.  
    This lack of extra gas prevents  to purging the weld start  area 
    of moisture laden air. 
A test was made to check weld performance and 
potential shielding gas 
    savings using two cylinders of shielding gas on two adjacent welders instead 
of their pipeline gas supply.  One was set with their 
    standard flow control orifice system and a regulator providing a pressure 
    that matched their pipeline, 50 psi.  The other with a 
    regulator/flowmeter (also of a 50 psi design) using a 15  foot 
    GSS without their flow control 
    orifice.  Both steady state flows were set at 45 CFH.  Since welders stand side 
    by side, it was easy to observe the weld start quality!   Instantly the 
    welder using the 
    GSS noticed  improved  
starting.  After about an hour with observably better results the  
welding engineer suggested we lower the shielding 
    gas flow on the  welder with the 
    GSS to 35 CFH!  The same improved weld start quality 
was observed and the welder was "happy."  In 
fact even though we lowered the steady-state flow to 35 CFH there was still 
about the same controlled amount of extra gas available at the start (that 
stored in the  GSS 
hose when welding stopped.) The higher start gas flow rate established by the 
surge flow orifice in the 
    GSS 
maintained the higher flow at the start.   
This higher start flow rate quickly flooded and purged the weld start area of 
moisture laden air.  
It was this air that was casing 
excess spatter and lack of shielding on all their other welders! After about 4 hours of observation it was obvious the spatter 
    at the weld start was less with the GSS.  
We also measured a reduced use of shielding gas of 25%.   
    After several months of testing to check this one system during windy days etc, 
    this shop now has 
    GSS's installed on all 50 welders!    
Bottom Line - - "Some extra 
gas flow at the start is very beneficial."  In addition, after about a year 
of use their gas supplier called to see if their business had turned down since 
they were using about 30% less gas- it had not! 
Second Case:  A review of the shielding gas 
    flow rates in a shop with 100 welders revealed the amount of excess gas flow 
    on each welder. 
    DETAILS: A shop with ~100 MIG welders tried to 
    reduce gas waste by installing flowmeters with flow controls at the wire feeders. These were connected by a gas 
    hose to a 50 psi shielding gas pipeline. Most of the flowmeters were model L-32 
    (shown at right)  which is designed to read accurately at 50 psi inlet 
    pressure, so the flow readings 
    are direct and accurate. 
    As when mounting a flow control orifice at the wire 
    feeder, this approach eliminates the start surge flow but there is insufficient 
    extra gas available to purge air from the weld start area and 
    MIG gun nozzle.  It is if you're starting in air!  As expected, 
    the welders tried to compensate by increasing the steady state flow! However increasing the steady state flow can only partially help as a substitute for quickly needing extra gas at the weld start! it also wasted much more gas than moving the flowmeter to the wirefeeder reduced! 
    The following was observed: 
      |  | 
      ~50% of the welders were set at ~50 
      to 55 CFH.  None were found lower than that flow level. |  |  | 
      ~25% of the welders were set near the 
      top of the flowgauge, which for this model is 70 CFH. |  |  | 
      The remaining ~25% had the flow ball 
      pinned to the top of the flow tube.  In our Lab we have measured 
      flows with this model of 150 CFH when the needle valve is fully opened and 
      the float ball pinned to the top of the flow tube! |  
    Conclusion: 
    Trying to compensate for the lack of sufficient extra start gas, the welders 
    set the steady state flow far higher than needed.  Any flow over 50 to 
    60 CFH is also pulling air into the gas stream and is counter productive! Therefore increasing the steady state flow to the average 60 to 70 CFH observed, increased gas usage far more than the observed decrease in initial gas surge!!   | 
  
    | 
    Question:  
    
    But we use a flow control orifice just to limit start surge flow and still 
    control the steady flow with a flowmeter at the gas source.  Is that a 
    problem? 
    Answer:   
    That will eliminate 
    the problem of excess gas surge but depending on the orifice size may not 
    supply sufficient extra gas.  We have found most commercially available 
    peak flow control orifices are actually not large enough to optimize start 
    surge flow rate.  In addition you may be doing that since you perceive 
    your saving gas.  You can hear the reduction that occurs in initial gas 
    surge, right?  Yes the surge flow is reduced and you can hear the difference.  However if you put a pressure gauge in 
    the gas 
    delivery hose, you will see it still reaches the pipeline pressure (or with 
    cylinder gas supply the regulator pressure) when welding stops!  The 
    pressure will reduce to what is needed to flow the required amount of gas 
    when welding starts (usually about 4 or 5 psi.)   Where does that 
    extra gas go?  It is wasted almost as if you did not have the orifice 
    in place!  It just takes longer to be expelled at the rate set by the 
    orifice!  You may save some gas, may 10% of the surge waste.  Our
    GSS saves about 80% of the gas waste!  
    It pays for itself in a matter of weeks and includes, as part of its 
    patented design, a surge flow limiting orifice at the feeder/welder end. 
    
    Check it out 
    
    Want More Details 
    About Extra Gas Needed at Weld Start? | 
  
    | See Other 
    Questions and Answers; Click Link Below: | 
  
    | 
      Q&A About Ideal Gas Delivery Systems | 
  
    | Q&A About Automatic Flow Compensation |